Good evening, I have an odd confdition occurring in a sequencing program that was written in Siemens Graph. I am fairly new to Siemens, but after reading the programming manual it is my understanding that when a step is active and the interlock condition is true the tag assigned as an output should be 1. I have a step that occasionally becomes active with a true interlock and the output doesn't go to 1.

Is there a scan issue or could there be logic elsewhere stopping the sequencer from running? I have attached a screenshot of the condition.

Thanks
Brad

IMG_2671.jpg
 

Similar Topics

Can someone explain the order of processing the actions of a step...is it top - bottom see attachment for reference. Does it process the blkmov...
Replies
1
Views
2,075
the plant I am supporting uses a siemens graph function to do some of the step procedures. in several steps it waits for the step to execute for...
Replies
1
Views
767
I'm still getting used to working with Siemens Step 7 Classic, and WinCC in the Simatic Manager package. I need a trend line on the MP377 HMI, and...
Replies
2
Views
1,841
I am using Graph for controlling 4 pallet stops. I am also using the supervision control on the last step that makes sure the pallet reached it's...
Replies
4
Views
2,028
I am working with a customer template who uses pre and post instructions in Graph. I have not used these before in Graph, and I am trying to...
Replies
3
Views
1,386