Right Track Revision

Leon

Member
Join Date
Mar 2007
Location
Ohio
Posts
75
I had several issues on the other post that I got all turned around with. Does the attached look any better? Jan-June, 2nd thru the 5th day of the week, (Don't think I need RTC:0.DAY but it would not hurt anything), 20th thru 40th minutes on the 10th hour of the day to the run output O:0/0.

Leon
 
I think RTC:0.DAY is the day within the month (e.g 1-31) so your example would only run on the 2nd through the 5th of the month assuming it met the Day Of Week test.
 
Bernie, sounds logical except then I can't fogure out why the lo & hi limit for the month. Unless you have to use one limit test for every month and change the days in RTC:0 Day and use one for every month.

Thanks, Leon
 
From original thread...
Leon said:
Does any one know how accurate a timer that times for 28,800 minutes (8 hrs) 3 times a day to a counter for 21 counts (7 days) via a limit test, then does another set of 21, then another 21 then repeat the cycle. For 3 seperate 7 day cycles for alternate operations, to run 24/7 all year long. Seconds/minutes/or hours guess. I have this running and a few minuts a year would not hurt but a few hours would.

Leon
Leon, maybe you should go back to using the PLC timer and utilize the RTC to reset it at a precise time. Then you can acheive you original goal (which isn't completely clear BTW) without having to be concerned with how many days are in each month.

Or perhaps even better to just look for a transition past midnight to increment a "day counter" and trigger your sequence with that...
 

Similar Topics

Have a fairly simple project wherein id like to monitor half a dozen Rh/temp sensors for dewpoint along with a few temp only sensors. i studied...
Replies
4
Views
2,870
Hello all! I've started writing my program for my machine, and I thought I'd post the first section of it for some constructive critism. This is...
Replies
3
Views
2,300
Hi all, I have a project that deals with dyeing clothes: 1)Operation will be started by a foot pedal or a 2 hand safety switch. 2)2 piston will...
Replies
6
Views
1,882
This is my first attempt to use a RTC in a 1500. I attached an example to run an output on the 5th day of the week in months 1-5 at 9:35M until...
Replies
7
Views
2,014
hi guys, I have a question regarding AB RIO, basically just wanna know if what I'm thinking in my head is how it will actually work. I have a...
Replies
6
Views
5,767