DOW in SLC504

I do not think you have a day of the week in a SLC504. You have the date S:39-S:37. You may be able to create code that looks at the date and gives you the day of the week.
 
mhopley said:
S:53 in a 5/05, this might be the same for later firmware 5/04.

worth a check?
Opps.... Same in a 5/04 but it is defind as "Reserved/Clock Calander Day of the Week".
 

Similar Topics

Got a repaired laptop back from warranty and loaded it up with all my software, unfortunately with my version V32.03 Studio 5000 I cannot change...
Replies
3
Views
186
I am attempting to generate a VBA script within FactoryTalk View SE to open a Google Chrome webpage (PI Vision) when an object is right-clicked...
Replies
2
Views
109
Hello. I am rebuilding an HMI from 2003 with the new software Factory Talk Optix. I have a pop up box with a trendline on it. I want the ability...
Replies
0
Views
146
Hello, since i am starting using intouch, i need some help Actually i want to make in intouch a String input field. The operator has to insert a...
Replies
1
Views
330
Hi everyone! Accidentally closed it and it wont appear again. Checked and unchecked the option and seem to make no difference. Running v7.10.00...
Replies
16
Views
1,904
Back
Top Bottom