I’m using a SLC 5/05 and a Panelview Plus 1000. I’m using the RecipePlus programming, the question I have is with the Status Tag and the Percent complete tag. With the examples I have (from AB) shows the tags (status and percent complete) in the tag browser. I have refreshed all folders and I still don’t see the tags. Do I have to create these tags? Or did I miss something? Thanks for your help!!
 
Configuring ReipePlus tags! I have found the recipes have 2 tags settings that are used to determine the results of various recipe operations during runtime. The first is "status" tag and the second is called the "percent complete tag" But I still don't know where to find them?
 
You need to go into the Recipe Plus Editor's General tab and assign those tags yourself. Basically you can assign any PLC tag to those fields and they are updated with the info automatically.
 

Similar Topics

Hello everyone, I am new to factorytalk and have started getting more in depth. We have one machine that i am looking for some variables that are...
Replies
0
Views
962
Hi, I have set up some recipes on a Panelview plus (2711P-T7C21D8S). Everything works great and I am data logging to a CF Card. I am using...
Replies
0
Views
1,282
Hi, I am new to the forum and fairly new to working with PLCs. I am currently self-teaching while working on a project for my company. I am...
Replies
3
Views
2,123
I’m looking to store my recipes on a USB stick. I’m using a PanelView Plus, I have created the path in setup in the following ways...
Replies
1
Views
4,867
When I test run an application I made, the "current value" column in the RecipePlus table comes up empty (picture attached). Does this have to do...
Replies
1
Views
1,618
Back
Top Bottom