GX Developer

ahargrave

Member
Join Date
Sep 2010
Location
NE Tennessee
Posts
9
Hello all,
I am making my first attempt at a program change on an FX2N-32M PLC using GX Developer ver. 8.78G.
I have figured out how to get my modifications done, but now I can't figure out how to get the program to convert or whatever the equivalent of "verify project" on RSLogix500 is.

Message I keep getting is "Ladder not converted. Are you sure you want to delete the Unconverted ladder?"

I would like to make my changes offline, verify and save the program so I don't interrupt production for more than the time it takes to download.

any help would be appreciated

AH :unsure:
 
Last edited:

Similar Topics

I'm trying to verify a project with a PLC. The Transfer Setup menu item is grayed out and every time I click Verify with PLC, I get an error...
Replies
1
Views
44
Well, I've decided to start a new project, and like all projects, it has already gone horribly wrong. I purchased a PLC device (supposedly a...
Replies
2
Views
111
Does anybody have any samples of how to "Create and Use" UDT's in CCW Developer Edition? (I am using v22) I can't find any information from...
Replies
3
Views
311
I'm trying to manually convert a Beijer E200 HMI project onto to a new Mitsubishi GOT gs2107-wtbd. The PLC is a very old A-series AS1CPU and is...
Replies
1
Views
381
Hi One of the PLC's that I maintain/update is a Mitsubishi Q-Series, probably installed about 10 years ago. At the moment, ALL the wires from...
Replies
13
Views
1,170