G'day Guys,
I have a S7-314C-2 DP Processor (6ES7 314-6CF00-0AB0) which has a full rack this has a IM365 module which breaks it out another rack with a spare slot.
I need to add a CP343 Lean module (Ethernet card) to the system yet Hardware manager won't allow the CP343 Lean to sit on the rack with a spare slot (I guess this is because the CP343 would bottleneck at the IM365?) hence I need to move a I/O module from the first rack to the second to allow me to place the CP343 on the same rack as the 314C. Is there an easier way to do then than having to A. Physically swop a card to make space on the same rack as the 314C and B. If I have to swop the cards do I manually have to reconfigure all the addresses using a global change?
I'm really after a couple of pointers as to problems I may encounter or tips to make this easier/less risk to production
Cheers.
Rob
I have a S7-314C-2 DP Processor (6ES7 314-6CF00-0AB0) which has a full rack this has a IM365 module which breaks it out another rack with a spare slot.
I need to add a CP343 Lean module (Ethernet card) to the system yet Hardware manager won't allow the CP343 Lean to sit on the rack with a spare slot (I guess this is because the CP343 would bottleneck at the IM365?) hence I need to move a I/O module from the first rack to the second to allow me to place the CP343 on the same rack as the 314C. Is there an easier way to do then than having to A. Physically swop a card to make space on the same rack as the 314C and B. If I have to swop the cards do I manually have to reconfigure all the addresses using a global change?
I'm really after a couple of pointers as to problems I may encounter or tips to make this easier/less risk to production
Cheers.
Rob