Right now I am trying to control the temperature of a furnace.

Is it possible to program a PIDE for getting to a certain temperature (Starting at 300ºC to 400ºC for example) BUT in a time of 5 hours and later with the same furnace and PIDE make the same operation but in a shorter or longer time.

Another example might help:

From 100ºC to 200ºC in 3 hours, later from the 200ºC to 400ºC in 7 hours... etc etc, is it possible with the same PIDE?:confused:

I dont know if I am explaining myself.🔨

Thanks!
 
My first idea was to create an equation of the process and then subtitute the x variable for getting the sp in certain time and then change the SP.

Seems a little complicated but possible. Im trying to find a better way to do it
 

Similar Topics

Greetings ... someone sent me a request for some student handsouts that I developed ... turns out that I had this hosted on my business website...
Replies
0
Views
153
Hello im using PIDE in rslogix 5000 - mode is DEPENDENT. im using it to control the temperature, via burners. im having some problems with...
Replies
10
Views
5,148
While troubleshooting control issues due to windup, it would be helpful to be able to view the error term due specifically to the error term in...
Replies
5
Views
1,903
Hi all, Having some issues setting up a PIDE Cascade control loop. Have been trying to go through the Wp008 doc but there's probably something...
Replies
9
Views
5,729
I have an application that I was wondering if these function blocks could help me out. I work at a hydro-dam (less than 4 MWatts), and we control...