Good Day,
We are stuck in a serious issue, please see below for details and give your valuable feedback.
- There are two PLCs running on site one is M340 and other is Quantum PLC.
- Both PLCs are sharing data with each other on ENET link and both have remote IO racks which are installed recently.
- Now we are having issue on Quantum side, the Quantum PLC stops and its heartbeat becomes zero after 22 to 24 hours.
- Then a reset of Quantum PLC resolves the issue and bring the PLC in function.
- All IO racks and modules installed n these racks are working fine, field to card communication is fine.
- Before the addition of remote IO racks, the communication was fine. We haven't came across this problem before.
- But after the addition the PLC was fine for 2 to 3 days.
Please help and share your valuable suggestions in this regard.
Regards,
Jawad Rasool
We are stuck in a serious issue, please see below for details and give your valuable feedback.
- There are two PLCs running on site one is M340 and other is Quantum PLC.
- Both PLCs are sharing data with each other on ENET link and both have remote IO racks which are installed recently.
- Now we are having issue on Quantum side, the Quantum PLC stops and its heartbeat becomes zero after 22 to 24 hours.
- Then a reset of Quantum PLC resolves the issue and bring the PLC in function.
- All IO racks and modules installed n these racks are working fine, field to card communication is fine.
- Before the addition of remote IO racks, the communication was fine. We haven't came across this problem before.
- But after the addition the PLC was fine for 2 to 3 days.
Please help and share your valuable suggestions in this regard.
Regards,
Jawad Rasool