Hi
Here's the situation:
1. We will install two air compressors, one will be the main supply while the other will be the back up. Both these compressors are connected to the same air tank, which supplies the whole production area.
2. A pressure sensor will be installed on the air tank, initially the compressor A will run till the required pressure is reached. Now, if the pressure has gone down to a minimum level due to peak production, compressor B will backup compressor A.
3. The above stated sequence will go on until sometime (let's say after 1 week). After 1 week, the compressor will switch over automatically, compressor B will be the main supply & compressor A will be the back up.
4. This switchover will go on constantly to protect the compressor from over heating.
Is this sequence possible? how?
Here's the situation:
1. We will install two air compressors, one will be the main supply while the other will be the back up. Both these compressors are connected to the same air tank, which supplies the whole production area.
2. A pressure sensor will be installed on the air tank, initially the compressor A will run till the required pressure is reached. Now, if the pressure has gone down to a minimum level due to peak production, compressor B will backup compressor A.
3. The above stated sequence will go on until sometime (let's say after 1 week). After 1 week, the compressor will switch over automatically, compressor B will be the main supply & compressor A will be the back up.
4. This switchover will go on constantly to protect the compressor from over heating.
Is this sequence possible? how?