Good afternoon,
We are developing an application for a client, and he has some P_Seq blocks from PlantPax in order to control the phases of the process.
The ladder uses equipment phases for each step of the process (for example, cleaning, heating, etc...).
We need to add a phase that will run at the same time as other steps, and to have freedom of choice. For instance, we can start phase 1 and phase 6 (new phase) at the same time, phase 6 being independent of any other phases, but we also need to be able to start only phase 1 and phase 6 individually.
Does P_Seq allow parallel phases? Any tips on how to do it using Equipment Phases in Studio 5000?
Thank you very much.
We are developing an application for a client, and he has some P_Seq blocks from PlantPax in order to control the phases of the process.
The ladder uses equipment phases for each step of the process (for example, cleaning, heating, etc...).
We need to add a phase that will run at the same time as other steps, and to have freedom of choice. For instance, we can start phase 1 and phase 6 (new phase) at the same time, phase 6 being independent of any other phases, but we also need to be able to start only phase 1 and phase 6 individually.
Does P_Seq allow parallel phases? Any tips on how to do it using Equipment Phases in Studio 5000?
Thank you very much.