This is just a shot in the dark but I'm trying to figure out what happened last night. Any help would be appreciated.

New clamps were added to some nest stations last week and somehow for startup this morning some but not all logic driving those clamps were missing from the PLC.

Things I know happened:

1) Power was lost to the line (PLC and programming terminal also lost power)
2) The initial person to troubleshoot had to open up the most recent program and go online. Doesn't look like they downloaded to the processor as all the datatables were still correct (part tracking and such). They would be at the previous saved state if he downloaded.

My thought is that the final edits were left testing and not assembled and the program wasn't saved with the testing edits. Does this make sense? Would testing edits be lost when the power gets cycled?

I'm running RSLogix 5000 v20.1 with 1756-L73S ControlLogix5573S Safety Controller
 

Similar Topics

Hi all, I have a power & free conveyor line with a series of machines / stations around it. Each station is controlled with a 5/03 connected to...
Replies
15
Views
3,838
Hi Guys, Can ControlLogix with Modsim32 for Modbus Server Testing? I have ControlLogix via Anybus Modbus TCP and I need to Test the...
Replies
6
Views
250
Hello all, looking for ideas on getting some basic training done, I need to practice on maintenance timers and bypass switches (with a Factory...
Replies
5
Views
1,275
I have a project in FTV ME (Studio v13) that I'm trying to apply security to a few buttons/setpoints. I have 4 users: Anonymous Logon, DEFAULT...
Replies
1
Views
764
I have a customer asking me to do some testing on non Rockwell I/O. They want to see if it will work. Thats simple hookup a PLC, put the IO in the...
Replies
4
Views
1,097
Back
Top Bottom