Hello every one,
I am using Schneider PLC CPU P266 140-CPU-671-60 in redundant configuration. I want to power off both Schneider CPU due to some work. Both CPU having Battery inside. Both PLC CPU LCD display not showing battery fault.

My question is, if I switched off & ON both CPU power then is there any loss of program inside PLC CPU or any SCADA set-point will reset..??

Please suggest...

Thanks
 
It depends how the plc is setup in the config. Software might write default values to certain %MW.
Make a data backup of the cpu's. If values are different after bootup you can always load the backup you saved.
 

Similar Topics

Hi Guys, First time posting here. I see a lot of useful information on this website. I was hoping someone could help me with a problem I am...
Replies
3
Views
2,948
Hello, I have S7-417-4H CPU having Modbus TCP/IP communication with Schneider PLC. Modbus TCP/IP communication was working. But since S7-417-4H...
Replies
4
Views
6,241
Hi all, I'm newbie about Schneider PLC M340 family, someone knows if is possible change the CPU IP address by means of some instruction to use...
Replies
3
Views
7,885
Hello, As part of our project, we are using an M241 controller. This controller interfaces with an industrial computer and a router via a switch...
Replies
2
Views
54
Hi Please I have zeilo smart relay #SR2A201BD but I don't have it's programming cable. Can I use any general usb/rs232 converter? Or need...