Old October 3rd, 2018, 10:49 AM   #1
milmat1
Member
United States

milmat1 is offline
 
milmat1's Avatar
 
Join Date: Aug 2005
Location: North Carolina
Posts: 175
Help with spec sheet ??

My friends,
I would like your suggestions here. I am developing a spec sheet to be filled out by the sales / mechanical dept. The purpose is to get me the information I need to properly design the control system.

We are an OEM building machinery for several industries, including material handling, bulk materials, brick handling, sawing equipment etc. Almost always standard 480V 60hz machines with PLC control and at least one touch screen hmi. Safety systems including zone control.

What would you want on such a spec sheet ?


Plant Voltage?
Environment ?

Temperature ?
Hazardous location Y/N ?
Type of hazard ?


Name some items you would want to know before beginning ?
__________________
"Forgiveness is easier to obtain than Permission"!


MATT
  Reply With Quote
Old October 3rd, 2018, 10:56 AM   #2
Dravik
Member
United States

Dravik is offline
 
Join Date: Jun 2008
Location: New York
Posts: 1,378
Regulatory and AHJ requirements outside of normal compliance requirements. (IE, for example compliance with CFR 21 Part 11 for Pharma industries)

Safety requirements
Ergonomic Requirements
Language Requirements
  Reply With Quote
Old October 3rd, 2018, 11:44 AM   #3
James Mcquade
Member
United States

James Mcquade is offline
 
Join Date: Oct 2007
Location: Tennessee
Posts: 2,231
Since you are the oem, your customer is to provide you with the specs.

questions I would ask.
what is the machine and what does it do
what is the poser requirements
what is the preferred plc and hmi
what plc software does the company have
what is the environment that the equipment is to be located !!!

Details up front is time consuming, BUT will save your rear end in the long run!
the more you ask, the more you know and learn, the more the price stays the same or goes up.

we always spell out what we are providing in detail.
if we get the job and quote is as a regular environment and the customer fails to tell us its a classified area, we have our quote we sent to them to fall back
on.

lots of other questions, but this is a start.
james
  Reply With Quote
Old October 3rd, 2018, 11:56 AM   #4
milmat1
Member
United States

milmat1 is offline
 
milmat1's Avatar
 
Join Date: Aug 2005
Location: North Carolina
Posts: 175
Quote:
Originally Posted by James Mcquade View Post
Since you are the oem, your customer is to provide you with the specs.

questions I would ask.
what is the machine and what does it do
what is the poser requirements
what is the preferred plc and hmi
what plc software does the company have
what is the environment that the equipment is to be located !!!

Details up front is time consuming, BUT will save your rear end in the long run!
the more you ask, the more you know and learn, the more the price stays the same or goes up.

we always spell out what we are providing in detail.
if we get the job and quote is as a regular environment and the customer fails to tell us its a classified area, we have our quote we sent to them to fall back
on.

lots of other questions, but this is a start.
james

Thank You !
This is the type of info I am looking for. I seem to get bitten on the rear end with every project because of this lack of communications...
__________________
"Forgiveness is easier to obtain than Permission"!


MATT
  Reply With Quote
Old October 3rd, 2018, 05:36 PM   #5
Tom Jenkins
Lifetime Supporting Member
United States

Tom Jenkins is offline
 
Tom Jenkins's Avatar
 
Join Date: Apr 2002
Location: Milwaukee, WI
Posts: 5,908
HMI requirements - color, screen size, etc.
Selector switches, pilot lights, pushbuttons, manual override requirements
Communications requirements for SCADA, protocols, etc.
Customer preferred PLC brand
Field instruments to be provided and powered
  Reply With Quote
Old October 11th, 2018, 03:34 PM   #6
milmat1
Member
United States

milmat1 is offline
 
milmat1's Avatar
 
Join Date: Aug 2005
Location: North Carolina
Posts: 175
Quote:
Originally Posted by Tom Jenkins View Post
HMI requirements - color, screen size, etc.
Selector switches, pilot lights, pushbuttons, manual override requirements
Communications requirements for SCADA, protocols, etc.
Customer preferred PLC brand
Field instruments to be provided and powered

Great Choices !!
__________________
"Forgiveness is easier to obtain than Permission"!


MATT
  Reply With Quote
Old October 11th, 2018, 10:36 PM   #7
James Mcquade
Member
United States

James Mcquade is offline
 
Join Date: Oct 2007
Location: Tennessee
Posts: 2,231
I would also ad what type of plc programming to use an what to exclude.

we use ladder logic only.
we do not allow fuzzy logic, grafcet, structured text, function blocks, sequencers, fifo.
ladder logic only and have the program given to maintenance to look at first.
the reason is that most maintenance personnel understand basic ladder logic.

james
  Reply With Quote
Old October 12th, 2018, 03:53 AM   #8
cardosocea
Member
United Kingdom

cardosocea is offline
 
Join Date: Nov 2016
Location: Fields of corn
Posts: 1,080
I doubt that most companies would contact you and not give this, but I would nevertheless ask about their HMI and PLC programming standards.
  Reply With Quote
Old October 12th, 2018, 10:59 AM   #9
James Mcquade
Member
United States

James Mcquade is offline
 
Join Date: Oct 2007
Location: Tennessee
Posts: 2,231
Specify the brand names and model #'s for the plc with spare requirements, hmi brand, scada brand and tag size with spares.
Specify everything !, or you may be forced to accept what they give you
which can turn out to be a boat anchor.

SPECIFY that all cylinders have sensors at each end for example.
running a bunch of cylinders using timers is a total waste of time!
load cells are to be rated for impact shock which means a that a 25 lb load cell must be rated for 250 lbs due to shock or they will only last for a month or 2, then they wear out.
string pots must have mechanical support such that the end of the pot does not bend ad the connection point and break due to fatigue.

james
  Reply With Quote
Old October 12th, 2018, 11:18 AM   #10
Rson
Member
United States

Rson is offline
 
Join Date: Jun 2017
Location: Michigan
Posts: 40
It depends on what type of controls you deal with often. For me the first questions I have to ask here are:

Is the machine indoors or outdoors?
Desired \ Required panel rating? (NEMA 4, 4x, 12, etc)
Does this have to be UL certified?
Control voltage: 24VDC or 120VAC?
How many motors, what HP rating for each, and VFD or Contactor control?
Local \ Remote modes required for each motor?
Are we using a PLC\HMI? (Yes, unfortunately, I still design relay panels every now and then)
PLC Brand \ Series
HMI Brand \ Series
Communications protocol
Interlocks (with Plant via ethernet \ dry contacts \ connector \ etc)

Based on that information alone, I have a pretty good idea of panel size and cost.

I'll also ask for them to either give me a sequence of operations (or at least how they think it should run) or I'll take the information above and write my own sequence to give to them. Sequences written out is a really easy way to communicate with people who don't understand controls (ie - almost all project managers)
  Reply With Quote
Reply
Jump to Live PLC Question and Answer Forum

Bookmarks


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Topics
Thread Thread Starter Forum Replies Last Post
Mitsubishi MX Sheet Excel addon doomsword LIVE PLC Questions And Answers 6 February 7th, 2017 12:00 PM
FactoryTalk SE alarm history data logging to separate Excel Sheet minaykha LIVE PLC Questions And Answers 1 April 29th, 2016 07:53 AM
RSLogix 5000 FB sheet size russrmartin LIVE PLC Questions And Answers 4 June 15th, 2006 11:37 AM
sheet edge detectors ldavis7999 LIVE PLC Questions And Answers 8 November 9th, 2003 01:24 AM
opensource PLC projects in C... s_viswesh LIVE PLC Questions And Answers 13 October 17th, 2002 05:39 PM


All times are GMT -5. The time now is 02:56 PM.


.