Progress Bar

arakhl

Member
Join Date
Jan 2020
Location
US
Posts
9
Hello Everyone

I need to create a progress bar

is it possible to di it nn FactoryTalk View?

I know it is possible in excel with VBA

Thank You
 
What are you visualizing the progress of ?

In general, the horizontal Fill animation for a Rectangle object is how you would create a "Progress Bar" in FactoryTalk View.
 
You can do it by creating an object and using Animation --> Fill. Simply tag it to a register in the PLC and fill that register. I recommend using the setting "Use constant" for the expression range.

Ken beat me to the response!
 
Last edited:
Thanks guys, I will try it
I have a button which is creates a backup of recipe that needed. ( recipe meaning the process of the parameters).
The process takes about 50 seconds and while it backing up, I can't do anything until the process has been complete. Progress bar will be helpful visually that there is a process going and you need to wait until it finishes.🍻
 

Similar Topics

Show me how you do Progress Bars I know how to create one, but I was wondering if anyone has some cool graphics that they would like to share. I...
Replies
8
Views
2,860
I've done 40-some of these installations over the past 6 months but this is the first time I encountered this and so far, I am unable to resolve...
Replies
4
Views
1,231
Good morning, I am currently working on the LogixPro Advanced Batch #2 Multiple Mode of Operation and got stuck very close to completion. Link...
Replies
3
Views
2,218
Kindly, while opening a copy of a Simatic project, the manager requested a Pdm conversion, which we started. But the PDM project converter is...
Replies
0
Views
937
Hi I've modified an iFix application and seem to be getting this fault everytime I run the project. Even when I am in workspace I get the error...
Replies
0
Views
5,417