I have a ABB robot and a Compactlogix PLC. There is a festo linear drive with a camera on it. There is also a fixed camera. The product has 10 lanes and is indexed on a common conveyor. The robot programmer wants control of the linear drive and both camera's. I the PLC programmer want control of the linear drive and the 2 camera's and I want to tell the robot when to pick and if rejected to pick again this makes the PLC master and will tie up with the recipes etc. This is the complicated part as product 1 then 2 etc is needed in sequence. If 2 fails on camera 1 then go get another product from 2 but if camera 2 fails then then product 1 is needed again then retest of product 2 etc. The robot programmer has won but not with out a fight. What are the forums feelings sequential robot programming ie if on then .. else .. or real time ladder logic...
__________________
Artificial Intelligence - Genuine programmers headache
|
|
|
|
#2 |
|
Lifetime Supporting Member + Moderator
|
From personal expierence i always go the plc side for this sort of thing, mainly for ease of support later down the line.
I have just done a robot retrofit with an obsolete robot and a beckhoff control system with only the runtime, you cant change anything you are stuffed.... At least with the siemens kit i put in for the conveyor etc it can be altered at a later date (look at S5 for examnple or PLC5's)
__________________
Regards Dave "When you are courting a nice girl an hour seems like a second. When you sit on a red-hot cinder a second seems like an hour. That's relativity." Albert Einstein (1879-1955) |
|
|
|
#3 |
|
Member
![]() Join Date: Dec 2004
Location: SE Michigan
Posts: 2,083
|
Same here. I've got several robot (ABB & Fanuc) cells in the works right now and I've designated the PLC as the master. The Robot is programmed as a slave, follows orders to do a task and then wait for the PLC to instruct it to do the next. Much easier debugging on the PLC end.
Of course, the "up" side is that by the robot programmer taking on more responsibility, he has to follow the project longer than you will.
__________________
"You can live to be a hundred if you give up all the things that make you want to live to be a hundred." Woody Allen |
|
|
|
#4 | |
|
Member
![]() Join Date: Oct 2005
Location: Chicago
Posts: 1,366
|
Quote:
Upside, since techs do mess with the Robot pendant and such, they cannot screw up anything since desicion making resides on the PLC side. I also control the Vision systems via PLc logic and desicion making, reject, double pick etc. |
|
|
![]() |
| Bookmarks |
| Currently Active Users Viewing This Thread: 1 (0 members and 1 guests) | |
| Thread Tools | |
| Display Modes | |
|
|
Similar Topics
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Rant about Safety | brucechase | LIVE PLC Questions And Answers | 25 | August 11th, 2009 12:08 PM |
| Regarding Simatic S5 PLC | srikrish | LIVE PLC Questions And Answers | 1 | June 10th, 2009 11:06 AM |
| PC to PLC Protocol | TheRixta | LIVE PLC Questions And Answers | 13 | December 17th, 2008 12:56 PM |
| Upgrading PLC 5/25 to PLC 5/30. What to take good care of? | ckchew666 | LIVE PLC Questions And Answers | 4 | August 18th, 2005 09:14 PM |
| PLC Programming.... or what... cars & motorcycles? | Terry Woods | LIVE PLC Questions And Answers | 53 | July 25th, 2005 06:42 PM |