RickParrot
Member
Good morning, All...
I am currently trending with a Micrologix 1100 for a very rare fault on PLC process. I've set up the Trending Graph with all my inputs. Problem is, I can't stand there and wait for 8 hours for the fault to pop up.
Is there anyway I can stretch the recording time of the Trending Graph? Can I program the Trending Graph to "freeze" when the fault is detected?
Thanks:site:
I am currently trending with a Micrologix 1100 for a very rare fault on PLC process. I've set up the Trending Graph with all my inputs. Problem is, I can't stand there and wait for 8 hours for the fault to pop up.
Is there anyway I can stretch the recording time of the Trending Graph? Can I program the Trending Graph to "freeze" when the fault is detected?
Thanks:site: