What is meant by cross referencing in step 7? What is it used for and how is it done?
Also what are MPI connections?
Thanks

Tom

___________________-
Alea Jacta Est
 
Cross-referencing shows you where an address is used throughout a program i.e. in which blocks and which network within that block.

MPI connections are normally 3-3 and 8-8.
 
Step 7

Thanks for reply on cross referencing.

Is this done with the programmer plugged into a live PLC or can it be done just by looking at the PLC program on the programmer?

Also what does MPI stand for, and what is it used for?
I'm still fairly new to this
Many Thanks,

Tom
 
You can generate and view a cross reference without being on-line i.e. just looking at the program.
MPI stands for multi-point interface, I think.
MPI is Siemens' own comms protocol. It can be used to connect two or more PLCs together on an MPI network or connect a PLC to an HMI.
 
wglespaul said:
What is meant by cross referencing in step 7? What is it used for and how is it done?

Step7 do it itself. In the program view put focus to some variable name (or absolute address) and push the right mouse button. Select 'Go to Location'. Rest part you can see yourself.

wglespaul said:
Also what are MPI connections?

RS485 based Multi Point Interface. Normally cabling from the CPU can be less than 50 meters without repeaters. Good practice is put repeaters in the PLC cubicle and each Control panel where are OP-panels or where you need outlet for programming.

mpirepeaters.jpg
 

Similar Topics

The past week we received a new piece of equipment from Germany which utilizes siemens controls. Typically in our company we use A.B. controls for...
Replies
4
Views
50
the conveyor can stop because of a safety sensor or safety switch. And also it can stop because of an object jam detector sensor. If the conveyor...
Replies
5
Views
133
Good Day to all of you, this is my first post, i will try to explain as best as possible, english is not my natural language. I am performing an...
Replies
0
Views
29
Hi All, Someone at work has put a PLC system on my desk, that's just been taken off an idle production line. He said "It's an S7 PLC. We don't...
Replies
10
Views
206
I have a project to automate four generator sets. The system will monitor and store the load demand of the factory. Once there's Power outage, the...
Replies
0
Views
57
Back
Top Bottom