Hi all,
I got involved recently in a oil and gas Pipeline project, we have 5 DCS at each tank farm and a SCADA to monitor the dispatch and reciept of the pipelines,we have an OPC interface between the DCS and SCADA at each of the 5 locations,we are still at the design stage ,now how to decide which one should be Master and Client in this OPC interface.....shall the DCS be server and the SCADA be the client of vice versa , what are the pros and cons for each scenario plz advise
I got involved recently in a oil and gas Pipeline project, we have 5 DCS at each tank farm and a SCADA to monitor the dispatch and reciept of the pipelines,we have an OPC interface between the DCS and SCADA at each of the 5 locations,we are still at the design stage ,now how to decide which one should be Master and Client in this OPC interface.....shall the DCS be server and the SCADA be the client of vice versa , what are the pros and cons for each scenario plz advise