I'm doing the programming for a new piece of equipment we're installing in the mill. I'm only adding logic to an existing program. This is the most programming I've done (I mostly do troubleshooting and process improvement). Can someone check this routine and let me know if it looks kosher?
This logic is meant to control a log deck, two reception conveyors, a bump stop, log clamp, saw, and log loader. The only thing it's missing is control for the saw stroke because I'm doing that in a separate routine once the VFD is installed.
All the physical I/O is mapped in a separate routine.
This logic is meant to control a log deck, two reception conveyors, a bump stop, log clamp, saw, and log loader. The only thing it's missing is control for the saw stroke because I'm doing that in a separate routine once the VFD is installed.
All the physical I/O is mapped in a separate routine.