GX IEC Developer task-pool problem

IanJohnston

Member
Join Date
Jun 2003
Posts
4
Hi,

GX IEC Developer (ver 4 & 5) & Q02 cpu.

I decided I needed a POU that will only run say every 4000ms (4 secs), so I created a new entry in the task pool and specified:-

Prio=10
Interval = T#4000ms

I'm finding that ok the POU doesn't run for 4 secs after everything else is running, but from that point onwards it seems to be running full whack.

I'm using a Mits GOT930 terminal which works by way of direct memory access, so the parameters on the LCD are actual PLC memory locations. I can see them delay for 4 secs but then continually refresh.
There's no other POU's updating the same memory locations.

I was expecting the data on my GOT terminal to update once say every 4 secs.

Any ideas?

Ian.
 

Similar Topics

Hi everyone, I'm working on a Mitsubishi Q series PLC whose code was developed in Mistubishi's GX IEC Developer v7.04. I looked online for GX IEC...
Replies
9
Views
1,474
Hi everyone, I'm working on a Mitsubishi Q series PLC whose code was developed in Mistubishi's GX IEC Developer v7.04. I looked online for GX IEC...
Replies
0
Views
497
Hello, i want to do a device backup but can´t find it. Someone remembers? :huh:
Replies
1
Views
878
I reposted this as I had mistakenly put IX developer in the title (it was a long day) :zzzzz: I have a policy of always verifying code before I...
Replies
1
Views
1,465
Hey, I have a small problem that I hope someone here could help me with. I'm trying to set up a transparent mode so I can monitor my program...
Replies
2
Views
1,858
Back
Top Bottom