fran007
Member
I have severals Power Generators of different Sizes connected to more than 20 Loads.
I'm reading the Load (MW) and Breaker Position for each Generator and each Load connected to the System.
When one of the generators open with load (Failure) I need to make a Load Shedding, removing a closer ammount of load from the system (Opening the Breakers)
The loads are variables, so I need to find the way to sheeding the load or the sum of the loads that are closer to the failed generator.
For Example:
A Generator with 5.94 MW Fail and I have the following load connected:
Load 1: 2.31 MW
Load 2: 3.52 MW
Load 3: 3.14 MW
Load 4: 4.25 MW
Load 5: 2.93 MW
Load 6: 3.89 MW
Load 7: 4.56 MW
Load 8: 2.67 MW
Load 9: 1.82 MW
Load 10: 0.98 MW
etc...
I need to Open the breakers for the Load or the Loads SUM closer to the load of the generator failed (In this case 5.9 MW).
I'm using Twincat (IEC 61131-3 PLC), I can use any of the programming lenguage.
Any Idea or Recomendation will be appreciated.
I'm reading the Load (MW) and Breaker Position for each Generator and each Load connected to the System.
When one of the generators open with load (Failure) I need to make a Load Shedding, removing a closer ammount of load from the system (Opening the Breakers)
The loads are variables, so I need to find the way to sheeding the load or the sum of the loads that are closer to the failed generator.
For Example:
A Generator with 5.94 MW Fail and I have the following load connected:
Load 1: 2.31 MW
Load 2: 3.52 MW
Load 3: 3.14 MW
Load 4: 4.25 MW
Load 5: 2.93 MW
Load 6: 3.89 MW
Load 7: 4.56 MW
Load 8: 2.67 MW
Load 9: 1.82 MW
Load 10: 0.98 MW
etc...
I need to Open the breakers for the Load or the Loads SUM closer to the load of the generator failed (In this case 5.9 MW).
I'm using Twincat (IEC 61131-3 PLC), I can use any of the programming lenguage.
Any Idea or Recomendation will be appreciated.