Hello Guys
i have recently been asked to look at a job,consisting of modbus and 5 allen bradley PLC's and around 30 racks
i have been told that the plc's are totally overloaded
controlnet is being used also,i wonder if you could give me some pointers on what to look for in regard to overloading/loading
my first thought is that too complicated code could be slowing down the processors,i am not a programmer but instrument guy,so i will be concentrating on the cabling etc
i would welcome your advice
i have recently been asked to look at a job,consisting of modbus and 5 allen bradley PLC's and around 30 racks
i have been told that the plc's are totally overloaded
controlnet is being used also,i wonder if you could give me some pointers on what to look for in regard to overloading/loading
my first thought is that too complicated code could be slowing down the processors,i am not a programmer but instrument guy,so i will be concentrating on the cabling etc
i would welcome your advice