Likely Site Acceptance Test.
When a plant buys a piece of equipment, two common milestones (of many) are a FAT (Factory Acceptance Test) and SAT (Site Acceptance Test). The purchaser visits the OEM to validate the equipment before it ships to site (FAT), then once the equipment is up and running in the plant, it is often subject to real world production validation (SAT).