We ran into a problem with a festoon system that we are installing and I was just seeing if anyone had any advice.
We are using flat cabling running down a track through about 12 trolleys (hanging overhead of a transfer cart). The trolleys are not wide enough to accommodate 4 cables that we have to install (only 3). Does anyone know if it's legal to double up the cables (stack two in the clamps)? Right now there are 3 cable setting side by side and that is fit in the clamp.
Thanks!
We are using flat cabling running down a track through about 12 trolleys (hanging overhead of a transfer cart). The trolleys are not wide enough to accommodate 4 cables that we have to install (only 3). Does anyone know if it's legal to double up the cables (stack two in the clamps)? Right now there are 3 cable setting side by side and that is fit in the clamp.