I try to get user application software from cpu which writed using loadder language or any one of IEC languages.
I forget how i can differentiate between upload and download?
i think upload to get program from plc, and download to send the program to plc.
Is that correct?
 
I am still paranoid about the use of those two terms. About 25 years ago, when I was young and ****y, I was working in a plant that had a Westronics "chart recorder /logger, that displayed all the plant data to the operators. ie it was the total "brains" of the plant.
I took it upon myself (nobody asked me) to get a pc to "talk" to this device. I found an old floppy disc with some dos type software, made up a rs232 lead and congratulated myself in getting it working first time.

I decided how clever, I would be, if I made a "backup" of the recorder,
I obviously got "upload" and "download" mixed up, probably ignored some "overwrite" warning and long story short, 5 seconds later, I had replaced the entire memory of the recorder with my blank file.
The entire plant now had no information, I had no idea where any of the sixty or so instruments were connected, what they were scaled to etc , I had to manually enter each "point" , guess the scaling and ask the operator, do you remember what "point 5 used to be etc etc. The operator had to "blindly" run the plant, the worst two days, I ever had and all self inflicted. lol
 
Last edited:
I am still paranoid about the use of those two terms.


I try to always include TO and FROM whenever I use upload/download, to try to be clearer: Download to the PLC/Upload from the PLC, etc. If I just say "download the program" there's more room for confusion.
 
I try to always include TO and FROM whenever I use upload/download, to try to be clearer: Download to the PLC/Upload from the PLC, etc. If I just say "download the program" there's more room for confusion.

Way back in the days of DOS, A-B software used to say "Upload from the PLC" and "Download to the PLC". Later versions they left off the "to" and "from" and there has been confusion ever since. I think that was the ICOM Ladder Logistics software. IIRC 6200 used "Save" and "Restore" instead of upload and download.

OG
 
I all ways say Download starts with a D so I remember Download is Dangerous .
Crazy I know but that is the way I remember it.
 

Similar Topics

Good people of PLCs.net, I am currently working with an HMI that is advantech 1250H, that communicates with a 1769 Compact logix and Currently...
Replies
2
Views
84
Hello, I have a machine with a 1756-L72 Controllogix PLC and 1756-EN2T network card, and PanelView Plus 7 HMI. I am using RSLogix V20.05.00...
Replies
12
Views
950
Hi everyone, i have multiple Omron hmi terminals in the plant and i need to upload each program. i have an ns8-tv01b-v2 terminal in the office...
Replies
8
Views
683
Hi all, I have existing S7 200 smart PLC system, I don't know what software version they used to program it. I use microwin smart version 2.3 to...
Replies
0
Views
519
Hi all, i have multiple Omron units at the plant and some have analog, rtd, thermocouple, ethernet cards, maybe other specialty cards, i'm just...